The 2# The Hot Test of Slab Continuous Casting Machine of Jingang Group was Carried out Successfully and Put Into Operation

November 30,2021

  Recently, the 2# slab continuous casting of Shanxi Jingang Intelligent Manufacturing Technology Industrial Co., Ltd. (hereinafter referred to as "Jingang Group") undertaken by Sino-heavymach successfully passed hot test. This is the second (210, 230) mm× (900 ~ 1300) mm two machines two strands slab continuous casting machine that passed hot test successfully contracted by Sino-heavymach after the 1# slab continuous casting machine in July. At present, the two continuous casting machines are both put into operation normally. 

  During the installation and commissioning process of 2 # continuous casting machine, on the basis of the commissioning experience of 1# continuous caster, the project team fully adopted the unique rapid installation technology of the segment foundation frame, so that the installation and rough adjustment of the segment foundation frame, which usually takes one month to be completed were completed in 5-7 days, and the accurate adjustment which previously needed 15 days only took 2 days. The measurement work that previously needed 5 operators and crane cooperation to be completed was reduced to 3 operators without the cooperation of crane.  

  By improving method, the erection and construction period of the two sets slab caster was shortened from 5-6 months to 3-4 months so as to save time for the client to put into operation at an early date and create conditions for the client to realize the full production of the two slab caster, which was highly praised by the leaders of Jingang Group. 

  At present, 1# and 2# slab casters run stably and the performance indicators of products are good to create a great economic and social benefits for client, laying a more solid foundation for the in-depth cooperation between Sino-heavymach and Jingang Group.